RFP 25-1150: Progressive Design-Build for ANPCC I, II, III Roof Renovations

Southcentral Foundation (SCF) is pleased to provide this public notice regarding the solicitation of detailed proposals from qualified Progressive Design-Build Teams for the design, supply, and construction of the roof replacement and renovations to the Anchorage Native Primary Care Center (ANPCC) I, II, III.

The Scope of Services is further defined and provided in the Exhibit A to this RFP. Proposers shall subcontract with other firms, if deemed necessary, to complete the tasks described in this RFP

RFP25-1150 Progressive Design-Build for ANPCC I,II,III Roof Renovations

Addenda

Request for Proposal Release date:     March 7, 2025
Proposal Due Date:                               April 4, 2025 by 3PM Alaska time

IMPORTANT NOTICE TO BIDDERS: Bidders must register with the SCF Contact Person via email using the link below. Failure to register with the SCF Contact Person may result in the rejection of a proposal.

RFP SCF25-1154 – DB ANPCC III ICT Furniture Replacement

SCF is soliciting detailed proposals from qualified teams interested in providing Design-Build services and cost estimating to replace sit-stand desk furniture and/or furnishings for the Integrated Care Team (ICT) open office workspaces within the Anchorage Native Primary Care Building III (ANPCC III).  Minor architectural, mechanical, electrical and data port construction is anticipated to accommodate the new furnishings. This building is located in Anchorage, Alaska.

The Scope of Services is further defined and provided as Exhibit A to this RFP. The Proposer shall subcontract with other firms, if deemed necessary, to complete the tasks described in this RFP.

RFP SCF25-1154 – DB ANPCC III ICT Furniture Replacement

EXHIBIT D_SCF Div 1 02-10-25

EXHIBIT-E_SCF-PCC-III-Clinic-Conformed-Set_Electrical-Drawing-Sheets-Only

Addendum 1

Updated RFP Registration date from Wednesday March 5, 2025, by 3 pm to Thursday March 6, 2025, by 1:30 pm

Addendum 2, I & II

Add Liquidated Damages, Retainage, & Contingency, Exhibit D to Exhibit F, add Exhibit F

Exhibit F

Request for Proposal Release date: February 26, 2025
Proposal Due Date: March 21, 2025, by 3 pm

IMPORTANT NOTICE TO BIDDERS: Bidders must register with the SCF Contact Person via email using the link below. Failure to register with the SCF Contact Person may result in the rejection of a proposal.

Request for Proposals (RFP): SCF25-1159-Quyana Clubhouse & Intensive Case Management Building Replacement Construction Manager/General Contractor Services

Southcentral Foundation (SCF) is pleased to provide this public notice regarding the solicitation of detailed proposals from Bidders interested in providing a Quyana Clubhouse & Intensive Case Management Building Replacement Construction Manager/General Contractor Services.

Notice of this RFP will remain posted until deadline for proposal submittal.  All information and details regarding this RFP are as presented in the RFP document, provided here in Adobe Acrobat format.

Request for Proposals (RFP): SCF25-1159-Quyana Clubhouse & Intensive Case Management Building Replacement Construction Manager/General Contractor Services

Exhibit D: Sample Contract Documents and Forms
AIA A133-2019 , SCF-Modified Form of Agreement Between Owner and Construction Manager as Constructor

AIA A201-2017, SCF-Modified General Conditions of the Contract for Construction

Reference 1:

SCF Eagle Street Development-Prelim Geotechnical Summery

10% Concept Design Package, Spark Design, Date 11/04/2024

Plat with Easements

Addendum 1:

  1. SCF Division 1 Specifications
  2. SCF Design Construction Standards
  3. 3.1 RFP Schedule Update

Addendum 2:  

1. Updated RFP Due date from Wednesday March 5th to Monday March 10th, 2025, 3pm AKST

Addendum 3

  1. Answers to questions and comments Issuance #1

Addendum 4

1 Updated RFP Due date from Monday March 10th to Wednesday March 12th 2025, 12pm AKST

Addendum 5

1   RFP Responses to Questions, Addendum 5

2   Summary Matrix of Cost Allocation

3   SCF25-1159 Addendum 5, RFP Sec 5.1 Update

4   Updated A133-2019, with updated contingency language, 3%

Plans Holders List

Request for Proposal Release date: February 6th, 2025
Proposal Due Date: March 12th, 2025 @ 12PM AKST

IMPORTANT NOTICE TO BIDDERS: Bidders must register with the SCF Purchasing Agent via email using the link below. Failure to register with the SCF Contact Person may result in the rejection of a proposal.